Client: Petrochemical
Contract Amount:
Project Length:
Equisol Contact: Mike Cooper    484.571.9360
 
Description: improved control via communications system, equipment improvements to reduce molds fouling due to poor control

Petrochemical plant was experiencing serious problems with the molds fouling due to poor control.

EquiSol worked with the corporate engineering, corporate IT, and the local water treater to design and install a fully redundant control system that was tied into the plant's LAN. We also gave them a MODBUS TCP/IP interface so that the operation could be monitored remotely from the corporate headquarters in the mid-west.


Based on this success, they have decided to make this plant standard for all their facilities.


The work included:

  • System Design.
  • Final tie-ins at the Chiller Plant.
  • Termination’s, calibration, start up and training of the Chiller Plant control system.
  • Installation of the MU flow meter on both chillers.
  • Final tie-ins at the Expansion Plant.
  • Termination’s, calibration, start up and training of the Expansion Plant control system.
  • LAN tie-in.
  • MODBUS TCP/IP tie-in to the existing WonderWare HMI.

 

 
 